ASX Announcement 10 July 2026
NORTH AMERICA'S LARGEST COMMERCIAL DLE
UNIT ARRIVES AS PRAIRIE LITHIUM ADVANCES
TOWARDS FIRST PRODUCTION
HIGHLIGHTS
• North America's largest Direct Lithium Extraction (DLE) unit has arrived at the Prairie Lithium
Project in Saskatchewan, Canada, marking another major milestone toward Phase 1
commercial production.
• Arrival of the commercial-scale DLE unit significantly de-risks the project, building on the
existing on-site infrastructure of constructed production / disposal wells, and power
infrastructure.1
• 100% of Phase 1 lithium production is secured under the Company’s binding offtake agreement
with Hydro Lithium2
, providing a clear pathway to first revenue.
• The commercial-scale DLE unit is approximately 4 times larger than the commercial DLE
system currently deployed at Standard Lithium’s Arkansas project, highlighting the scale of
Prairie Lithium’s initial commercial development.3
• Arrival of the commercial scale DLE unit enables the next phase of installation ahead of
commissioning, as Prairie Lithium advances towards first commercial production in
Saskatchewan, one of the worlds top-tier, mining-friendly jurisdictions.4
Prairie Lithium Limited (ASX: PL9, OTC: PLIXF) (“Prairie”, “Prairie Lithium”, “PL9” or “the Company”),
a company focused on the sustainable development of the Prairie Lithium Project, in Saskatchewan, Canada,
is pleased to announce that North America’s largest commercial Direct Lithium Extraction Unit (DLE) has
arrived on site, marking another major milestone as the Company advances toward Phase 1 commercial
lithium production.
This arrival of the commercial-scale DLE unit represents a significant project de-risking event and enables the
next phase of equipment installation and commissioning, which remain targeted for Q4 2026. It complements
the substantial infrastructure already established on site, including production and disposal wells, electrical
infrastructure and the power transformer.
The commercial-scale DLE unit is approximately 4 times larger than the commercial DLE system currently
deployed at Standard Lithium’s Arkansas project, where a single column was installed in March 2024 and is
achieving industry-leading results 5 . This milestone demonstrates the scale of Prairie Lithium’s Phase 1
development and the Company’s ambition to become a leading commercial DLE producer in North America.
Lithium produced from Phase 1 operation is already secured under the Company’s binding offtake agreement
with Hydro Lithium, which will purchase 100% of Phase 1 lithium production, providing a clear pathway from
commissioning to first revenue.
This represents a significant de-risking event for the project, and complements infrastructure that is already
constructed onsite, such as the production wells, disposal wells, and the power transformer.
1 ASX Announcement – "Construction Nearing Completion with Fully Secured Offtake and Clear Path to First Revenue" – 13 April 2026
2
ASX Announcement – “Binding Offtake Secured for 100% of Phase 1 Production WITH ~AU$10M STRATEGIC COLLABORATION AND DEFINITIVE OFFTAKE” – 2 April 2026
3
NYSE Announcement – “STANDARD LITHIUM REACHES MAJOR OPERATIONAL MILESTONES AT ARKANSAS DEMONSTRATION PLANT” – 22 April 2026
4 ASX Announcement – "CONSTRUCTION NEARING COMPLETION WITH FULLY SECURED OFFTAKE AND CLEAR PATH TO FIRST REVENUE" – 13 APRIL 2026
5
NYSE Announcement – “STANDARD LITHIUM REACHES MAJOR OPERATIONAL MILESTONES AT ARKANSAS DEMONSTRATION PLANT” – 22 April 2026
Level 2, 10 Outram Street
West Perth WA 6005
T +61 (8) 6313 3936
E info@prairielithium.com
ASX: PL9
OTC: PLIXF
With the project's key infrastructure in place, a binding 100% offtake agreement secured and the commercial
DLE unit now on site, Prairie Lithium has assembled the critical components required to progress toward Phase
1 production and first revenue.
Figure 1: Prairie Lithium’s four-column Commercial Scale DLE Unit at Prairie Lithium site
Level 2, 10 Outram Street
West Perth WA 6005
T +61 (8) 6313 3936
E info@prairielithium.com
ASX: PL9
OTC: PLIXF
Figure 2: Prairie Lithium’s four-column Commercial Scale DLE Unit at Prairie Lithium site
Level 2, 10 Outram Street
West Perth WA 6005
T +61 (8) 6313 3936
E info@prairielithium.com
ASX: PL9
OTC: PLIXF
Prairie Lithium Executive Chairman, Paul Lloyd, commented:
“The arrival of North America’s largest commercial Direct Lithium Extraction unit marks another defining
milestone for the company as we advance towards becoming one of North America’s newest commercial
lithium producers.
“Over the past 18 months we have continued to execute against each of the major milestones required to
advance Prairie Lithium toward commercial production.
“We have de-risked the project through regulatory approvals, construction of key site infrastructure, securing
a binding 100% offtake agreement with Hydro Lithium and now the delivery of the commercial DLE unit.
“Supported by our existing infrastructure, scalable development model and binding offtake agreement, Prairie
Lithium is well positioned to become one of North America’s leading commercial Direct Lithium Extraction
projects.”
About the Prairie Lithium Project
PL9’s Prairie Lithium Project is located in Saskatchewan, Canada, one of the world’s top mining friendly
jurisdictions, with key infrastructure including electricity, natural gas, fresh water, paved highways and
railroads. The project is being advanced with a focus on scalable lithium brine production and efficient
development, leveraging existing regional infrastructure and the Company’s phased development model.
This ASX announcement is authorised for release by the Board.
For further information please contact:
SCAN ME
Mr. Paul Lloyd
Executive Chairman
Tel. +61 419 945 395
paul@prairielithium.com
Jane Morgan
Investor & Media Relations Manager
+ 61 (0) 405 555 618
jm@janemorganmanagement.com.au