CONSTRUCTION OF LITHIUM PLANT IN FULL
SWING AT PRAIRIE PROJECT
HIGHLIGHTS
• Piles and grade beams for the foundation have been installed at Pad #1, building construction
is now underway, and Prairie Lithium selected a prefabricated steel building system that
allowed wall panels to be manufactured in a controlled Canadian factory while power and
foundation work proceeded on-site, significantly shortening the schedule, reducing weather
risk, and providing a faster path for future expansion.
• Monetising the world-class 4,600,000-tonne LCE resource is in high gear with plant
construction in Saskatchewan, Canada, and 2026 will mark delivery of the largest, commercial
scale, Li-Pro Direct Lithium Extraction equipment ever built. )
• At the completion of construction, Prairie Lithium will be the first fully permitted lithium brine
producer in an established oilfield, utilising innovative lithium brine production from an
existing oil field that is likely to structurally change the rapidly evolving lithium market.
• Prairie Lithium seeks to become one of the leaders driving this structural change in the lithium
market.
• The shareholder value creation event of lithium production comes at an ideal time as lithium
commodity prices continue to strengthen, with 100% of initial lithium output already sold to
Hydro Lithium of Korea under an existing offtake agreement.
Prairie Limited (ASX: PL9 OTC: PLIXF) (“Prairie Lithium”, “PL9” or “the Company”), a company focused
on the sustainable development of the Prairie Lithium Project (“Prairie”), is pleased to announce that building
construction is on schedule at its flagship Pad #1 Commercial Facility site following the successful installation
of piles and grade beams for the building foundation. With foundation works complete, vertical construction is
now underway, marking a significant milestone in monetising Prairie’s world-class 4,600,000-tonne LCE
resource through plant construction in Saskatchewan, Canada.
Prairie Lithium has selected a prefabricated steel building system for the facility, with panels integrating
structural, insulation, air/vapor barrier, and exterior finish components into complete, load-bearing wall
assemblies. A critical benefit of this design is that wall panel fabrication occurred concurrently with on-site
power and foundation works completed in January and February. The wall panels were manufactured in a
controlled factory environment in Canada while foundation work progressed at Pad #1, significantly shortening
the overall on-site construction schedule, reducing exposure to weather variability, and providing an
accelerated pathway for future facility expansion.
2026 is expected to be a transformational year for the Company, with delivery of the largest Li-Pro Direct
Lithium Extraction (DLE) equipment ever built. Upon completion, Prairie Lithium is positioned to become the
first fully permitted lithium brine producer in an established oilfield. The Company’s innovative approach—
producing lithium from brine sourced from an existing oil field—has the potential to structurally change the
rapidly evolving lithium market, and Prairie Lithium seeks to be a leader in driving that change.
The commencement of lithium production represents a significant shareholder value creation event,
particularly as lithium commodity prices continue to strengthen. Importantly, 100% of initial lithium output from
the plant has been secured under an existing offtake agreement with Hydro Lithium of Korea, further
underpinning the commercial foundation of the project.
Level 2, 10 Outram Street
West Perth WA 6005 Australia
T +61 (8) 6313 3936
E info@prairielithium.com
ASX: PL9
OTC: PLIXF
Link to video of piles and grade beam foundations work is here: Prairie Lithium Facility Construction - Piles
and Grade Beam.
Figure 1: Piles being installed at Pad #1
Figure 2: Aerial view of Pad #1 during foundation construction
Level 2, 10 Outram Street
West Perth WA 6005 Australia
T +61 (8) 6313 3936
E info@prairielithium.com
ASX: PL9
OTC: PLIXF
Figure 3: Building materials arriving on-site
Prairie Lithium Managing Director, Paul Lloyd, commented: “The transition to full building construction at
Pad #1, following the successful installation of piles and grade beams, marks a major milestone as we advance
toward commercial lithium production in Saskatchewan. With plant construction now firmly underway, we are
accelerating the monetisation of our world-class 4.6 million tonne LCE resource.
By selecting a prefabricated structural panel system, we have been able to manufacture complete load-bearing
wall assemblies in a controlled Canadian factory environment while power and foundation works were
completed on-site. This parallel workstream significantly compresses construction timelines, reduces weather-
related risk, and provides a scalable, repeatable ‘cookie-cutter’ model that supports rapid future expansion.
Importantly, 2026 will see the delivery of the largest, commercial scale, Li-Pro DLE equipment ever built,
positioning Prairie Lithium to become the first fully permitted lithium brine producer in an established oilfield in
North America. Our innovative approach of producing lithium from brine sourced from an existing oil field has
the potential to structurally reshape the rapidly evolving lithium market, and we intend to be at the forefront of
that transformation.
With 100% of our initial production secured under an offtake agreement with Hydro Lithium of Korea, and
lithium prices continuing to strengthen, this milestone represents an important shareholder value creation event
at an ideal point in the commodity cycle.”
About the Prairie Lithium Project
PL9’s Prairie Lithium Project in Saskatchewan, Canada, is in one of the world’s top mining friendly jurisdictions.
The project has easy access to key infrastructure including electricity, natural gas, fresh water, paved highways
and railroads. The project also aims to have strong environmental credentials, with Prairie Lithium targeting to
Level 2, 10 Outram Street
West Perth WA 6005 Australia
T +61 (8) 6313 3936
E info@prairielithium.com
ASX: PL9
OTC: PLIXF
use less freshwater, land and waste, aligning with the Company’s sustainable approach to lithium
development.
This ASX announcement is authorised for release by the Board.
For further information please contact:
Mr. Paul Lloyd
Managing Director
Tel. +61 419 945 395
paul@prairielithium.com
Share your feedback
Discover