ASX Announcement 4 February 2026
CONSTRUCTION OF POWER INFRASTRUCTURE
FOR PRAIRIE PROJECT
HIGHLIGHTS
• SaskPower has commenced installation of grid power infrastructure at the Company's flagship
Pad #1 Commercial Facility site. It took only three months from the original submission to
installation, highlighting the Prairie Lithium Project's infrastructure advantage in Saskatchewan.
1.2 kilometres of powerlines were installed.
• The grid power connection will provide reliable, low-cost (USD ~$0.05 / kWh) electricity to the Pad
#1 wells and processing facility, enabling efficient operations for brine pumping, DLE processing,
and supporting infrastructure.
• This milestone significantly de-risks the project timeline by ensuring reliable, low-cost power
availability.
Prairie Limited (ASX: PL9, OTC: PLIXF) (“Prairie Lithium”, “PL9” or “the Company”), a company focused
on the sustainable development of the Prairie Lithium Project (“Prairie”), is pleased to announce that
SaskPower has commenced installation of grid power infrastructure at the Company's flagship Pad #1
Commercial Facility site. Approximately 1.2 km of powerlines were installed. It took only three months from the
original submission to installation, highlighting the Prairie Lithium Project's infrastructure advantage in
Saskatchewan.
The grid power connection will provide reliable, low-cost (USD ~$0.05 / kWh) electricity to the Pad #1 wells
and processing facility, enabling efficient operations for brine pumping, DLE processing, and supporting
infrastructure. SaskPower's involvement leverages the province's established and reliable energy network,
aligning with Prairie Lithium's strategy to utilise Saskatchewan's existing oil, gas and power infrastructure for
low-impact lithium development.
This milestone significantly de-risks the project timeline by ensuring reliable, low-cost grid power, which is
essential for the facility's operations.
Figure 1: Recently installed power lines to Pad #1 along the road
Level 2, 10 Outram Street
West Perth WA 6005 Australia
T +61 (8) 6313 3936
E info@prairielithium.com
ASX: PL9
OTC: PLIXF
Figure 2: SaskPower construction area for Transformer at Pad #1
Prairie Lithium Managing Director, Paul Lloyd, commented: “The commencement of grid power installation
by SaskPower at Pad #1 is a pivotal step toward commercial production. As the US Department of Energy
notes, ‘Electricity underpins every sector of the modern economy,’ and securing this connection ensures our
project is built on a foundation of reliable, low-cost energy. The rapid transition from approval to installation in
just two months highlights the significant infrastructure advantage of operating in a mature jurisdiction like
Saskatchewan. This milestone allows us to commission the facility quickly, integrate our DLE technology, and
bring our lithium resources online responsibly and efficiently.”
About the Prairie Lithium Project
PL9’s Prairie Lithium Project in Saskatchewan, Canada, is in one of the world’s top mining friendly jurisdictions.
The project has easy access to key infrastructure including electricity, natural gas, fresh water, paved highways
and railroads. The project also aims to have strong environmental credentials, with Prairie Lithium targeting to
use less freshwater, land and waste, aligning with the Company’s sustainable approach to lithium
development.
This ASX announcement is authorised for release by the Board.