ASX Announcement 30 April 2026
QUARTERLY ACTIVITIES REPORT
For the Period Ended 31 March 2026
HIGHLIGHTS
• Prairie advanced Pad #1 from enabling infrastructure to active building construction,
marking a major step toward first commercial production.
• SaskPower installed ~1.2 kilometres of powerlines to Pad #1, delivering reliable, low-
cost grid electricity to support brine pumping, Direct Lithium Extraction (DLE)
processing and associated infrastructure.
• Commercial-scale foundation work completed, including deep driven piles and
reinforced grade beams engineered to support heavy processing infrastructure.
• Vertical building construction commenced using a prefabricated steel building system,
with wall panels manufactured off-site in Canada concurrently with on-site foundation
works - shortening the overall schedule, reducing weather risk and supporting
repeatable expansion.
• Prairie continued to advance the 4.6 million tonne LCE indicated resource1
, with Pad #1
representing the first hub in the Company’s scalable, modular development strategy.
• Post quarter-end, executed a binding, definitive offtake with Hydro Lithium for 100% of
Phase 1 production (150tpa LCE), with Hydro Lithium providing ~A$10m of downstream
refining equipment, materially reducing the upfront capital required from Prairie Lithium
to get into first production.
Prairie Lithium Limited (ASX: PL9 OTC: PLIXF) (“PL9”, “Prairie Lithium” or the “Company”), a
company focused on the sustainable development of the Prairie Lithium Project (“Prairie”), is pleased
to provide an overview of the Company’s activities for the period ending 31 March 2026 (“Quarter” or
“Reporting Period”).
Prairie Lithium Managing Director, Paul Lloyd, commented:
“The March quarter marked the transition of Pad #1 from enabling works to active facility construction -
the point where engineered foundations, grid power from SaskPower, and the commencement of
vertical building come together to turn plans into production.
We are now executing what the Company believes is one of the most advanced Direct Lithium
Extraction opportunities globally, in one of the world's most supportive mining jurisdiction. Each
milestone this quarter compounds directly into our path to first production estimated to be in Q4 2026.
Since quarter-end we have also secured a binding offtake with Hydro Lithium for 100% of Phase 1, with
approximately A$10 million of downstream refining equipment provided by our partner, which materially
lowers the capital required to reach first revenue. Pad #1 is the first hub in a scalable, modular
development model, and the groundwork we are laying now is built to be repeated.”
1 ASX Announcement – “Prairie Project Production Approved & Project Update (Amended)” – 23 May 2025. Refer Appendix 1 for resource detail.
2 ASX Announcement – “North America’s First Lithium Brine Facility” – 17 February 2025. The Company confirms that it is not aware of any new
information that materially affects the information included in the original market announcement and that all material assumptions and technical
parameters underpinning estimates in the relevant market announcement continue to apply and have not changed.
Prairie
Lithium
Level 2, 10 Outram Street
West Perth WA 6005 Australia
T +61 (8) 6313 3936
E info@prairielithium.com
ASX: PL9
OTC: PLIXF
Figure 1: Aerial view of Pad #1 during foundation construction
Prairie Lithium Project
Prairie Project Development and Construction
During the Quarter, Prairie Lithium made significant progress advancing construction at its flagship
Pad#1 Commercial Facility site within the Prairie Project in Saskatchewan, Canada.
Power Infrastructure
On 4 February 2026, the Company announced that SaskPower had commenced installation of grid
power infrastructure at Pad #1. Approximately 1.2 kilometres of powerlines were installed, providing
access to reliable, low-cost electricity for brine pumping, DLE processing and associated infrastructure.
The rapid transition from application to installation highlighted the infrastructure advantages of operating
in Saskatchewan and materially de-risked the project timeline.
Figure 2: Power infrastructure installed at Pad #1
Prairie
Lithium
Level 2, 10 Outram Street
West Perth WA 6005 Australia
T +61 (8) 6313 3936
E info@prairielithium.com
ASX: PL9
OTC: PLIXF
Foundation & Construction Works
On 11 February 2026, the Company announced that construction crews had commenced installation
of deep-driven piles and reinforced concrete grade beams at Pad #1.
These engineered foundations are designed to support heavy processing infrastructure and long-term
facility integrity. This milestone followed completion of site preparation, geotechnical analysis,
permitting and power infrastructure installation.
Concurrent with these activities, prefabricated structural building panels were manufactured off site,
enabling parallel execution of construction workstreams.
On 5 March 2026, the Company announced that foundation works were completed, and vertical
construction of the building had commenced.
Figure 3: Installation of foundation piles at Pad#1
Corporate and Financial Position
The Company continues to maintain a solid financial position as it progresses construction activities.
As at 31 March 2026, Prairie Lithium held A$6.6 million in cash and cash equivalents, providing funding
support for ongoing development activities.
During the Reporting Period, the Company remained focused on disciplined capital allocation, directing
expenditure toward construction, project development, and advancing Prairie toward production.
Events Subsequent to Quarter End
On 2 April 2026, Prairie Lithium announced that it had executed a binding definitive offtake agreement
with Hydro Lithium for 100% of Phase 1 production, representing 150tpa of LCE2. This binding offtake
formalises the offtake Heads of Agreement signed with Hydro Lithium on 11 December 2025.
Under the agreement, Hydro Lithium will also provide and operate approximately A$10 million of refining
equipment for Phase 1, supporting a lower capital pathway to production.
Prairie Lithium has indicated that first production is targeted in Q4 20263.
3 ASX announcement 2 April 2026: Binding Offtake Secured for 100% of Phase 1 Production
Prairie
Lithium
Level 2, 10 Outram Street
West Perth WA 6005 Australia
T +61 (8) 6313 3936
E info@prairielithium.com
ASX: PL9
OTC: PLIXF
Outlook
Prairie is well-positioned as it moves into the next Quarter, having materially advanced Pad #1 through
critical infrastructure and construction milestones. With the Prairie Project progressing in a leading
North American jurisdiction, Prairie remains focused on translating construction momentum into
commercial readiness.
Prairie continues to position the Prairie Project as a 4.6 million tonne LCE indicated resource1
developed through a modular pad by pad strategy, with Pad #1 representing the first commercial hub.
The project is Canada’s first and only lithium brine facility approved for commercial scale production.
Figure 4: Building materials arriving on-site
Next Steps
In the upcoming Quarter, Prairie Lithium will focus on:
• Advancing building construction at Pad #1.
• Preparing for delivery and installation of commercial scale Li-Pro DLE equipment .
• Progressing the Prairie Project toward first production.
• Continuing to execute its scalable development strategy across the broader Prairie Project.
Prairie
Lithium
Level 2, 10 Outram Street
West Perth WA 6005 Australia
T +61 (8) 6313 3936
E info@prairielithium.com
ASX: PL9
OTC: PLIXF
About the Prairie Lithium Project
PL9’s Prairie Lithium Project in Saskatchewan, Canada, is in one of the world’s top mining friendly
jurisdictions. The project has easy access to key infrastructure including electricity, natural gas, fresh
water, paved highways and railroads. The project also aims to have strong environmental credentials,
with Prairie Lithium targeting to use less freshwater, land and waste, aligning with the Company’s
sustainable approach to lithium development.
Figure 5: Prairie Lithium’s Project Location
This ASX announcement is authorised for release by the Board.
For further information please contact:
Mr. Paul Lloyd
Managing Director
P: +61 419 945 395
E: paul@prairielithium.com
Jane Morgan
Investor & Media Relations Manager
P: +61 405 555 618
E: jm@janemorganmanagement.com.au
Competent Persons statement for Prairie and Registered Overseas Professional Organization (ROPO) and
JORC Tables
Gordon MacMillan P.Geo., Principal Hydrogeologist of Fluid Domains, who is an independent consulting geologist
of a number of brine mineral exploration companies and oil and gas development companies, reviewed and
approves the technical information pertaining to the exploration results and mineral resource estimates within the
release. Mr. MacMillan is a member of the Association of Professional Engineers and Geoscientists of Alberta
(APEGA), which is ROPO accepted for the purpose of reporting in accordance with the ASX listing rules. Mr.
MacMillan has been practicing as a professional in hydrogeology since 2000 and has 24 years of experience in
mining, water supply, water injection, and the construction and calibration of numerical models of subsurface flow
and solute migration. Mr. MacMillan is also a Qualified Person as defined by NI 43-101 rules for mineral deposit
disclosure. He has sufficient experience relevant to qualify as a Competent Person as defined by the ’Australasian
Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves – The JORC Code (2012). Mr.
MacMillan consents to the inclusion in this announcement of the matters based on this information in the form and
context in which it appears.
Prairie
Lithium
Level 2, 10 Outram Street
West Perth WA 6005 Australia
T +61 (8) 6313 3936
E info@prairielithium.com
ASX: PL9
OTC: PLIXF
Appendix 1 – Resource
Producing
Formations
Indicated Indicated
Seward 62,459 332,469
Flat Lake 4,076 21,697
Upper Wymark 110,674 589,118
Middle Wymark 449,381 2,392,055
Lower Wymark 97,223 517,518
Saskatoon 131,565 700,320
Total 860,000 4,600,000
Figure 6: Prairie Project Resource Summary. Representative lithium concentrations within the Resource area based on the
mass volume and brine volume estimates. The average lithium concentration across all zones over the Prairie Project land
permits is 98 mg/L.
Prairie
Lithium
Level 2, 10 Outram Street
West Perth WA 6005 Australia
T +61 (8) 6313 3936
E info@prairielithium.com
ASX: PL9
OTC: PLIXF
Appendix 2: Schedule of Mining Tenements
The following information is provided pursuant to Listing Rule 5.3.3 for the quarter ended 31 March
2026.
Project Claim Number Location Interest
Lordsburg LLP-211 to LLP-274 New Mexico, USA 100%
Lordsburg LLP-283 to LLP-298 New Mexico, USA 100%
Lordsburg LLP-307 to LLP-322 New Mexico, USA 100%
Lordsburg LLP2-1 to LLP2-96 New Mexico, USA 100%
Prairie Lithium S002/1 Saskatchewan, Canada 100%
Prairie Lithium S004/5 Saskatchewan, Canada 100%
Prairie Lithium S005/46-48, S005/58, S005/60 Saskatchewan, Canada 100%
Prairie Lithium S008/31-35, S008/41,
S008/49-54, S008/56,
S008/69-74, S008/77,
S008/86-99, S008/102-109
Saskatchewan, Canada 100%
Prairie Lithium S009/19, S009/24, S009/35,
S009/39, S009/41-44,
S009/50-53
Saskatchewan, Canada 100%
Prairie Lithium Canpar Holdings Ltd. File No.
M043397, M043398, M043399,
M043400
Freehold Royalties Ltd. File
No. M043402, M043403
Saskatchewan, Canada 100%
There were no tenements acquired or sold during the Quarter.
T +61 (8) 6313 3936
E info@prairielithium.com
ASX: PL9
OTC: PLIXF
Level 2, 10 Outram Street
West Perth WA 6005 Australia
Appendix 3: Exploration Expenditure and Payments to Related Parties
In line with its obligations under ASX Listing Rules 5.3.1 and 5.3.5, Prairie Lithium Limited notes the following
in relation to the period ended 31 March 2026 as advised in the Appendix 5B:
• exploration and evaluation expenditure primarily relates to work undertaken on the Prairie Lithium project
(classified as investing) and operating costs of the Lithium Research Centre (classified as operating);
• the only payments to related parties of the Company pertain to payments to executive directors for salary
and superannuation, non-executive director fees and consultancy fees.
Rule 5.5
ASX Listing Rules Appendix 5B (17/07/20) Page 1
+ See chapter 19 of the ASX Listing Rules for defined terms.
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
PRAIRIE LITHIUM LIMITED
ABN Quarter ended (“current quarter”)
15 008 720 223 31 MARCH 2026
Consolidated statement of cash flows Current quarter
$A’000
Year to date (9
months)
$A’000
1. Cash flows from operating activities
- -
1.1 Receipts from customers
1.2 Payments for
- (319)
(a) exploration & evaluation
(b) development - -
(c) production - -
(d) staff costs (229) (968)
(e) administration and corporate costs (794) (1,938)
1.3 Dividends received (see note 3) - -
1.4 Interest received 30 89
1.5 Interest and other costs of finance paid - -
1.6 Income taxes paid - -
1.7 Government grants and tax incentives - -
1.8 Other 84 84
1.9 Net cash from / (used in) operating
activities (909) (3,052)
2. Cash flows from investing activities
- -
2.1 Payments to acquire or for:
(a) entities
(b) tenements - -
(c) property, plant and equipment (668) (668)
(d) exploration & evaluation (433) (2,641)
(e) investments - -
(f) other non-current assets - -
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 2
+ See chapter 19 of the ASX Listing Rules for defined terms.
Consolidated statement of cash flows Current quarter
$A’000
Year to date (9
months)
$A’000
2.2 Proceeds from the disposal of:
- -
(a) entities
(b) tenements - -
(c) property, plant and equipment - -
(d) investments - -
(e) other non-current assets - 7,729
2.3 Cash flows from loans to other entities - -
2.4 Dividends received (see note 3) - -
2.5 Other - -
2.6 Net cash from / (used in) investing
activities (1,101) 4,420
3. Cash flows from financing activities
- 2,350
3.1 Proceeds from issues of equity securities
(excluding convertible debt securities)
3.2 Proceeds from issue of convertible debt
securities
- -
3.3 Proceeds from exercise of options - -
3.4 Transaction costs related to issues of equity
securities or convertible debt securities - -
3.5 Proceeds from borrowings - -
3.6 Repayment of borrowings - (5)
3.7 Transaction costs related to loans and
borrowings
- -
3.8 Dividends paid - -
3.9 Other – security bond refund - 151
3.10 Net cash from / (used in) financing
activities - 2,496
4. Net increase / (decrease) in cash and
cash equivalents for the period
4.1 Cash and cash equivalents at beginning of
period 8,746 3,162
4.2 Net cash from / (used in) operating
activities (item 1.9 above) (909) (3,052)
4.3 Net cash from / (used in) investing activities
(item 2.6 above) (1,101) 4,420
4.4 Net cash from / (used in) financing activities
(item 3.10 above) - 2,496
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 3
+ See chapter 19 of the ASX Listing Rules for defined terms.
Consolidated statement of cash flows Current quarter
$A’000
Year to date (9
months)
$A’000
4.5 Effect of movement in exchange rates on
cash held (174) (464)
4.6 Cash and cash equivalents at end of
period 6,562 6,562
5. Reconciliation of cash and cash
equivalents
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
Current quarter
$A’000
Previous quarter
$A’000
5.1 Bank balances 4,812 6,696
5.2 Call deposits 1,750 2,050
5.3 Bank overdrafts - -
5.4 Other (provide details) - -
5.5 Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
6,562 8,746
6. Payments to related parties of the entity and their
associates
Current quarter
$A'000
6.1 Aggregate amount of payments to related parties and their
associates included in item 1 493
6.2 Aggregate amount of payments to related parties and their
associates included in item 2 -
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and an
explanation for, such payments.
Amounts shown at item 6.1 comprise of payments to related parties (or their associates) for director and
administration fees paid during the current and previous quarters, including fees for services performed.
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 4
+ See chapter 19 of the ASX Listing Rules for defined terms.
7. Financing facilities
Note: the term “facility’ includes all forms of financing
arrangements available to the entity.
Add notes as necessary for an understanding of the
sources of finance available to the entity.
Total facility
amount at quarter
end
$A’000
Amount drawn at
quarter end
$A’000
7.1 Loan facilities - -
7.2 Credit standby arrangements - -
7.3 Other – equipment leases - -
7.4 Total financing facilities - -
7.5 Unused financing facilities available at quarter end -
7.6 Include in the box below a description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any additional financing
facilities have been entered into or are proposed to be entered into after quarter end,
include a note providing details of those facilities as well.
8. Estimated cash available for future operating activities $A’000
8.1 Net cash from / (used in) operating activities (item 1.9) (909)
8.2 (Payments for exploration & evaluation classified as investing
activities) (item 2.1(d)) (433)
8.3 Total relevant outgoings (item 8.1 + item 8.2) (1,342)
8.4 Cash and cash equivalents at quarter end (item 4.6) 6,562
8.5 Unused finance facilities available at quarter end (item 7.5) -
8.6 Total available funding (item 8.4 + item 8.5) 6,562
8.7 Estimated quarters of funding available (item 8.6 divided by
item 8.3)
5
Note: if the entity has reported positive relevant outgoings (ie a net cash inflow) in item 8.3, answer item 8.7 as “N/A”.
Otherwise, a figure for the estimated quarters of funding available must be included in item 8.7.
8.8 If item 8.7 is less than 2 quarters, please provide answers to the following questions:
8.8.1 Does the entity expect that it will continue to have the current level of net operating
cash flows for the time being and, if not, why not?
Answer: N/A
8.8.2 Has the entity taken any steps, or does it propose to take any steps, to raise further
cash to fund its operations and, if so, what are those steps and how likely does it
believe that they will be successful?
Answer: N/A
8.8.3 Does the entity expect to be able to continue its operations and to meet its business
objectives and, if so, on what basis?
Answer: N/A
Note: where item 8.7 is less than 2 quarters, all of questions 8.8.1, 8.8.2 and 8.8.3 above must be answered.
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 5
+ See chapter 19 of the ASX Listing Rules for defined terms.
Compliance statement
1 This statement has been prepared in accordance with accounting standards and policies which
comply with Listing Rule 19.11A.
2 This statement gives a true and fair view of the matters disclosed.
Date: 30 April 2026
Authorised by: The Board of Prairie Lithium Limited
(Name of body or officer authorising release – see note 4)
Notes
1. This quarterly cash flow report and the accompanying activity report provide a basis for informing the market about the
entity’s activities for the past quarter, how they have been financed and the effect this has had on its cash position. An
entity that wishes to disclose additional information over and above the minimum required under the Listing Rules is
encouraged to do so.
2. If this quarterly cash flow report has been prepared in accordance with Australian Accounting Standards, the definitions
in, and provisions of, AASB 6: Exploration for and Evaluation of Mineral Resources and AASB 107: Statement of Cash
Flows apply to this report. If this quarterly cash flow report has been prepared in accordance with other accounting
standards agreed by ASX pursuant to Listing Rule 19.11A, the corresponding equivalent standards apply to this report.
3. Dividends received may be classified either as cash flows from operating activities or cash flows from investing activities,
depending on the accounting policy of the entity.
4. If this report has been authorised for release to the market by your board of directors, you can insert here: “By the board”.
If it has been authorised for release to the market by a committee of your board of directors, you can insert here: “By the
[name of board committee – eg Audit and Risk Committee]”. If it has been authorised for release to the market by a
disclosure committee, you can insert here: “By the Disclosure Committee”.
5. If this report has been authorised for release to the market by your board of directors and you wish to hold yourself out as
complying with recommendation 4.2 of the ASX Corporate Governance Council’s Corporate Governance Principles and
Recommendations, the board should have received a declaration from its CEO and CFO that, in their opinion, the financial
records of the entity have been properly maintained, that this report complies with the appropriate accounting standards
and gives a true and fair view of the cash flows of the entity, and that their opinion has been formed on the basis of a
sound system of risk management and internal control which is operating effectively.
Share your feedback
Discover